The steps
- Check the parcelLook up your lot in ZIMAS: zone, Hillside Area, fire zone and any specific plan or overlay. Venice lots also need a coastal approval and a Venice Specific Plan review; see Coastal Zone ADUs.
- Prepare drawingsSite plan, floor plan, elevations, structural details and Title 24 energy compliance. Garage conversions also document the existing structure.
- SubmitOnline through ePlanLA, or in person by appointment.
- Plan check and clearancesLADBS reviews the building code and routes clearances: Bureau of Engineering (sewer availability, roof drainage, address), LA Fire Department (hydrants and access), City Planning (zoning), and LADWP if the work is within 10 ft of a utility easement.
- Permit issuedPay fees, including school fees for units over 500 sq ft.
- Build and inspectLADBS inspections through final, then the certificate of occupancy.
The coastal approval
Every Venice ADU is in the Coastal Zone. Near the beach (the dual permit area) a coastal permit is needed from both the City and the Coastal Commission; elsewhere the City's permit is the only one. Since AB 462, ADU coastal permits are on a 60-day clock without appeals of local ADU-only decisions. Details: Coastal Zone ADUs.
Review deadlines
State law puts LADBS on a clock: (Gov. Code § 66317)
- 15 business days to say whether the application is complete. If it doesn't, the application is deemed complete.
- 60 days from a complete application to approve or deny it, or it is deemed approved.
- The City must have an appeal process that decides within 60 business days.
The clock runs on a complete application. Corrections you resubmit, and clearances from other departments, are where most projects lose time.
Pre-approved standard plans
LADBS keeps a catalog of ADU Standard Plans already reviewed for the building code. The current list has 30 plans, from 280 to 1,200 sq ft and studio to three bedrooms. You buy the drawings from the firm that owns them; the City's own YOU-ADU is a 455 sq ft one-bedroom. Plan check still reviews your site: zoning, setbacks, foundation and utilities. (LADBS ADU Standard Plans)
Standard plans fit backyard ADUs. A garage conversion works with the garage you have, so it is drawn for your property.
Fees
- LADBS plan check and permit fees, based on the work.
- Impact fees only above 750 sq ft, proportional to the main house; no park fees or Affordable Housing Linkage Fee on ADUs.
- LAUSD school fees of $5.38 per sq ft on ADUs over 500 sq ft.
See fees under the rules for the citations.
Utilities and address
LADWP serves a lot with one electric service, and meters are grouped at the main house. If the ADU gets its own meter, it needs its own address approved by Public Works. (LADWP Electric Service Requirements, 2025 ed., § M) Sewer availability is cleared by the Bureau of Engineering during plan check.
Where to go
The nearest LADBS development services center is West LA, 1828 Sawtelle Blvd, 2nd floor, Los Angeles 90025. Most ADU applications are filed online through ePlanLA.